Case Study

Pre-cast

Project:

North Foreshore Film Studio

Main Contractor:

O'Hare & McGovern Construction

O'Hare & McGovern Construction

Project Engineer:

RPS Structural Engineers

Product:

Driven Pre Cast concrete Piles

Project details

Taranto have design, manufactured and installed the driven pre cast concrete piled foundations for the new North Foreshore Film Studios in Belfast.

The Foundation Package system comprises of 438 No pre-cast concrete piles installed to depths of 18m, and a substantial programme of on-site material and pile testing.